I & R Division Projects

A listing of Infrastructure and Regulation Division's capital projects and their current status. Click on a project's title for more information.

Resurfacing / Paving (3 Projects)

Road Plan - Roadway Resurfacing
25 of 30.21 Miles Completed ( 83%)
Active road resurfacing contracts will improve 30.21 centerline miles of paved roads through the end of January 2023. The total miles resurfaced will be updated periodically as projects are completed.

Andy Markunas (843) 915-5160
Road Plan - Dirt Road Paving
0 of 2.17 Miles Completed ( 0%)
Awarding Construction Contracts - 1.27 miles Under Design - 0.90 miles Total Miles = 2.17

Larry Hamilton (843) 915-5160
CTC - Dirt Road Paving
0 of 2.52 Miles Completed ( 0%)
Ready For Design - 1.10 miles Preparing to bid - 0.82 miles Under Construction - 0.60 miles Total Miles = 2.52

Larry Hamilton (843) 915-5160

Building (9 Projects)

Fire Training Center
Project Status: Delay
Estimated Completion Dates:
Design: TBD TBD
Permit: TBD TBD
Construction: TBD TBD
Row acquisition:
Property Acquisition: TBD TBD

New Fire Training Facility. Site and plans TBD
----------------------------
John Barnhill 843.915.5300
New Emergency Operations Center / E-911 Facility
Project Status: Completed Behind Schedule
Estimated Completion Dates:
Design: May 2020
Permit: October 2020
Construction: May 2022
Row acquisition:
Property Acquisition: January 2000

New two story EOC/E-911 facility.
----------------------------
Randy Webster 843-915-5150
Central Coast Complex - Replacement for 21st Ave. Building
Project Status: On Schedule
Estimated Completion Dates:
Design: November 2022
Permit: March 2023
Construction: TBD TBD
Row acquisition:
Property Acquisition: October 2021

Replace the existing Olin I Blanton building.
----------------------------
John Barnhill 843-915-5300
Longs Fire Station #13
Project Status: Completed Behind Schedule
Estimated Completion Dates:
Design: July 2020
Permit: January 2020
Construction: May 2022
Row acquisition:
Property Acquisition: October 2019

New Building to replace the existing Longs Fire Station
----------------------------
John Barnhill - (843) 915-5300
Library Administration Renovation
Project Status: Behind Schedule
Estimated Completion Dates:
Design: January 2021
Permit: January 2023
Construction: TBD TBD
Row acquisition:
Property Acquisition: January 2000

Renovate the Library Admin Building
----------------------------
John Barnhill 843-915-5300
Socastee Fire #1 Renovation
Project Status: On Schedule
Estimated Completion Dates:
Design: May 2021
Permit: May 2023
Construction: September 2023
Row acquisition:
Property Acquisition: January 2000

Enlarge the existing fire station
----------------------------
John Barnhill 843-915-5300
Shell Fire Station
Project Status: On Schedule
Estimated Completion Dates:
Design: December 2022
Permit: January 2023
Construction: Febuary 2024
Row acquisition:
Property Acquisition: January 2009

A New Shell Fire Station.
----------------------------
John Barnhill 843-915-5300
Forestbrook Fire #4
Project Status: On Schedule
Estimated Completion Dates:
Design: August 2022
Permit: January 2023
Construction: May 2024
Row acquisition:
Property Acquisition: November 2021

Relocating and expanding the existing Forestbrook Fire Station.
----------------------------
John Barnhill 843-915-5300
Nixionville / Wampee Fire Station
Project Status: On Schedule
Estimated Completion Dates:
Design: July 2021
Permit: January 2023
Construction: Febuary 2024
Row acquisition:
Property Acquisition: November 2021

A new combined fire station for the Nixionville and Wampee communities.
----------------------------
John Barnhill 843-915-5300

Drainage (2 Projects)

Cameron Village Emergency Outfall
Project Status: Completed On Schedule
Estimated Completion Dates:
Design: Febuary 2017
Permit: April 2017
Construction: August 2017
Row acquisition:
Property Acquisition:

Working to construct an emergency outfall to reduce flooding in Cameron Village. DDC study has been completed, now working with GSWSA on the emergency outfall. Outfall ditch was completed.
----------------------------
garigent@horrycountysc.gov
Southcreek at Myrtle Beach National Drainage
Project Status: Completed On Schedule
Estimated Completion Dates:
Design: April 2017
Permit: June 2017
Construction: August 2017
Row acquisition:
Property Acquisition:

Improve Drainage System in the National Drive area to reduce flooding.
----------------------------